Bath House Close, Godmanchester

24th March 2017

Godmanchester-4

Construction of 5 no Bungalows for MUIR Housing Group.


Located off a small shared drive within a dense residential development, this site owned by MUIR Group Housing had been stood for 8 years.

T. Balfe became involved and value engineered the scheme to make it viable for MUIR Housing Group. With T. Balfe undertaking the Design Build Package, a scheme involving 5nr Bungalows became a reality.

After completing a mass muck shift and archaeological works, ground was broken in June 2016 and handover completed on time and to a budget.


Duration of works: 28 weeks


Value of Works: £570,000


View more images →


Our work included:


    • Construction of 5 no residential bungalows and all associated works for the MUIR Housing Group.